Rivaan, Goregaon West

by M/s Meghna Infracon LLP · Goregaon West, Mumbai 400104 · Map

Launched
Jul 20244 yrs 5 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
85%Mid-construction
Booked (free sale)
71 of 7792% · 29 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale71 booked out of 77 units

Rehab29 units for existing members

Total 106 units. Rehab units are not for sale.

Project facts

1 BHK
66
2 BHK
23
Other units
17
Total units
106
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
77
Rehab units
29
Reserved units
33

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 80%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 85%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%71
100%50%0%68
100%40%0%56
80%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400104

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400104
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 5 mths3 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Sep 2027
Concrete structure (RCC)85%70%
Units booked (free sale)92%67%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Rivaan by M/s Meghna Infracon LLP is a 106-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in July 2024 with possession due in December 2028. 71 units booked out of 77 units for sale. The concrete structure (RCC) is 85% complete.

Read full summary

Rivaan is a BMC-sanctioned project by M/s Meghna Infracon LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800077162. It was launched in July 2024. It has 106 units in 1 building: 89 homes (1 and 2 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 106 units, 77 are for sale and 29 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started.

71 units booked out of 77 units for sale (92%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 50% to 85%.