Sheetal, Borivali West

by C H Patil And Sons Sheetal Project · Borivali West, Mumbai 400091 · Map

Launched
Jul 20244 yrs 8 mths promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
22 of 3563% · 26 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale22 booked out of 35 units

Rehab26 units for existing members

Total 61 units. Rehab units are not for sale.

Project facts

2 BHK
30
3 BHK
31
Total units
61
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
35
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 100%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%22
100%10%0%7
100%10%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400091

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400091
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 8 mths2 yrs 8 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Mar 2029May 2027
Concrete structure (RCC)100%100%
Units booked (free sale)63%79%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Sheetal by C H Patil And Sons Sheetal Project is a 61-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in July 2024 with possession due in March 2029. 22 units booked out of 35 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sheetal is a BMC-sanctioned project by C H Patil And Sons Sheetal Project in Borivali West, Mumbai 400091, registered with MahaRERA as P51800076973. It was launched in July 2024. It has 61 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 61 units, 35 are for sale and 26 are rehab units for existing members.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 20% complete.

22 units booked out of 35 units for sale (63%). Since the December 2025 update, 15 more units have been booked and the reported concrete structure (RCC) has gone from 10% to 100%.