Pranami Bliss, Andheri West

by Pranami Neev Realty Limited · Andheri West, Mumbai 400058 · Map

Launched
Jul 20242 yrs 9 mths promised
Possession (MahaRERA)
Apr 2027Not extended
Concrete structure
60%Mid-construction
Booked (free sale)
148 of 17087% · 64 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale148 booked out of 170 units

Rehab64 units for existing members

Total 234 units. Rehab units are not for sale.

Project facts

1 BHK
82
2 BHK
145
3 BHK
3
Other units
4
Total units
234
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
170
Rehab units
64

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 25%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%148
100%60%0%99
100%60%0%99
100%25%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400058

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400058
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths3 yrs 5 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Apr 2027Mar 2028
Concrete structure (RCC)60%23%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Pranami Bliss by Pranami Neev Realty Limited is a 234-unit MHADA-sanctioned project in Andheri West, Mumbai 400058, launched in July 2024 with possession due in April 2027. 148 units booked out of 170 units for sale. The concrete structure (RCC) is 60% complete.

Read full summary

Pranami Bliss is a MHADA-sanctioned project by Pranami Neev Realty Limited in Andheri West, Mumbai 400058, registered with MahaRERA as P51800077150. It was launched in July 2024. It has 234 units in 1 building: 230 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 234 units, 170 are for sale and 64 are rehab units for existing members.

Its registered possession date is April 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

148 units booked out of 170 units for sale (87%). Since the July 2026 update, 49 more units have been booked.