Romell Asrava, Andheri West
by Romell Realtor Developers Private Limited · Andheri West, Mumbai 400058 · Map
- Launched
- Sep 20244 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 62%Mid-construction
- Booked (free sale)
- 4 of 904% · 77 rehab units
- Buildings
- 40.8 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 90 units
Rehab77 units for existing members
Total 167 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 70
- 2 BHK
- 60
- 3 BHK
- 19
- 4 BHK
- 1
- Other units
- 17
- Total units
- 167
- Buildings
- 4
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 90
- Rehab units
- 77
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 62% | 0% | 4 | |
| 100% | 84% | 0% | 5 | |
| 100% | 52% | 0% | 1 | |
| 43% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400058
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 3 mths | 3 yrs |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2028 | May 2027 |
| Concrete structure (RCC) | 62% | 42% |
| Units booked (free sale) | 4% | 87% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Ananta, Andheri West
- Pranami Bliss, Andheri West
- Naumi Shresht, Andheri West
- Mesacon Crown, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ananta | October 2024 | March 2028 | 0% | 5 units booked out of 81 units for sale |
| Pranami Bliss | July 2024 | April 2027 | 60% | 148 units booked out of 170 units for sale |
| Naumi Shresht | June 2024 | March 2027 | 23% | – |
| Mesacon Crown | April 2024 | June 2027 | 100% | 37 units booked out of 40 units for sale |
About this project
Romell Asrava by Romell Realtor Developers Private Limited is a 167-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in September 2024 with possession due in December 2028. 4 units booked out of 90 units for sale. The concrete structure (RCC) is 62% complete.
Read full summary
Romell Asrava is a BMC-sanctioned project by Romell Realtor Developers Private Limited in Andheri West, Mumbai 400058, registered with MahaRERA as PR1180002400002. It was launched in September 2024. It has 167 units in 4 buildings: 150 homes (1, 2, 3 and 4 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 167 units, 90 are for sale and 77 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 62% complete, final finishes not started.
4 units booked out of 90 units for sale (4%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 84% to 62%.
Romell's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 25 |
|---|---|
| Total units across these projects | 1,599 |
| Completed without extending the possession date | 21 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 3 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 6 years 1 month |
| MahaRERA complaints (filed by or against the builder), all Romell projects | 4 (3 of 25 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.