Romell Asrava, Andheri West

by Romell Realtor Developers Private Limited · Andheri West, Mumbai 400058 · Map

Launched
Sep 20244 yrs 3 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
62%Mid-construction
Booked (free sale)
4 of 904% · 77 rehab units
Buildings
40.8 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 90 units

Rehab77 units for existing members

Total 167 units. Rehab units are not for sale.

Project facts

1 BHK
70
2 BHK
60
3 BHK
19
4 BHK
1
Other units
17
Total units
167
Buildings
4
Land
0.8 acres
Phases
1
MahaRERA complaints
1
Free-sale units
90
Rehab units
77

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)62%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 43%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 52%Jul 2026: Concrete structure (RCC) 84%Oct 2026: Concrete structure (RCC) 62%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 62%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%62%0%4
100%84%0%5
100%52%0%1
43%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400058

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400058
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 3 mths3 yrs
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2028May 2027
Concrete structure (RCC)62%42%
Units booked (free sale)4%87%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Romell Asrava by Romell Realtor Developers Private Limited is a 167-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in September 2024 with possession due in December 2028. 4 units booked out of 90 units for sale. The concrete structure (RCC) is 62% complete.

Read full summary

Romell Asrava is a BMC-sanctioned project by Romell Realtor Developers Private Limited in Andheri West, Mumbai 400058, registered with MahaRERA as PR1180002400002. It was launched in September 2024. It has 167 units in 4 buildings: 150 homes (1, 2, 3 and 4 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 167 units, 90 are for sale and 77 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 62% complete, final finishes not started.

4 units booked out of 90 units for sale (4%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 84% to 62%.

Romell's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA25
Total units across these projects1,599
Completed without extending the possession date21
Completed after an extension1
Lapsed0
Under construction3
Possession date extended on the builder's application2
Typical time from launch to 100% structure6 years 1 month
MahaRERA complaints (filed by or against the builder), all Romell projects4 (3 of 25 projects)

See all Romell projects →