Skip to main content

Ananta, Andheri West

by Jet Builders LLP · Andheri West, Mumbai 400058 · Map

Launched
Oct 20243 yrs 5 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
5 of 816% · 49 rehab units
Buildings
20.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 81 units

Rehab49 units for existing members

Total 130 units. Rehab units are not for sale.

Project facts

1 RK
8
1 BHK
29
2 BHK
46
3 BHK
36
4 BHK
2
Other units
9
Total units
130
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
81
Rehab units
49

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 73%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%5
73%0%0%0
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400058

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400058
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths2 yrs 9 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Mar 2028Jun 2027
Concrete structure (RCC)0%60%
Units booked (free sale)6%55%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Ananta by Jet Builders LLP is a 130-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in October 2024 with possession due in March 2028. 5 units booked out of 81 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Ananta is a BMC-sanctioned project by Jet Builders LLP in Andheri West, Mumbai 400058, registered with MahaRERA as PM1180002400036. It was launched in October 2024. It has 130 units in 2 buildings: 121 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 130 units, 81 are for sale and 49 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

5 units booked out of 81 units for sale (6%). Since the July 2026 update, 5 more units have been booked.