Metro Excellency, Malad West
by Tm Developer LLP · Malad West, Mumbai 400064 · Map
- Launched
- Oct 20244 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 60%Mid-construction
- Booked
- 128 of 20263% · 121 in Jul 2026
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 131
- 2 BHK
- 37
- Other units
- 34
- Total units
- 202
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 100
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 0% | 128 | |
| 100% | 35% | 0% | 121 | |
| 100% | 0% | 0% | 120 | |
| 70% | 0% | 0% | 13 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400064
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 2 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Dec 2028 | Nov 2027 |
| Concrete structure (RCC) | 60% | 60% |
| Units booked | 63% | 61% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Rashmi Signature, Malad West
- Redevelopment Of Kaveri Chsl, Malad West
- Shreeji Bliss, Malad West
- Redevelopment Of Glendon Chsl, Sheldon Chsl, Orlem Luciana Chsl, Malad West
- Vir Paradise, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rashmi Signature | July 2024 | August 2027 | 92% | 39 units booked out of 92 units for sale |
| Redevelopment Of Kaveri Chsl | July 2024 | March 2028 | 66% | 37 units booked out of 61 units for sale |
| Shreeji Bliss | July 2024 | January 2028 | 31% | 37 units booked out of 90 units for sale |
| Redevelopment Of Glendon Chsl, Sheldon Chsl, Orlem Luciana Chsl | July 2024 | November 2027 | 60% | 40 units booked out of 66 units for sale |
| Vir Paradise | March 2025 | November 2027 | 13% | 87 units booked out of 105 units for sale |
About this project
Metro Excellency by Tm Developer LLP is a 202-unit SRA-sanctioned project in Malad West, Mumbai 400064, launched in October 2024 with possession due in December 2028. 128 units booked out of total 202 units. The concrete structure (RCC) is 60% complete.
Read full summary
Metro Excellency is an SRA-sanctioned project by Tm Developer LLP in Malad West, Mumbai 400064, registered with MahaRERA as P51800077755. It was launched in October 2024. It has 202 units in 2 buildings: 168 homes (1 and 2 BHK) and 34 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.
128 units booked out of total 202 units (63%). Since the July 2026 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 35% to 60%.