Deepali Darshan J. P. Nagar Co-Operative Housing Society Limited, Goregaon East

by Westin Sankalp Developers · Goregaon East, Mumbai 400063 · Map

Launched
Aug 20242 yrs 4 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
70%Mid-construction
Booked (free sale)
2 of 633% · 13 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 6 units

Rehab13 units for existing members

Total 19 units. Rehab units are not for sale.

Project facts

1 BHK
4
2 BHK
11
3 BHK
4
Total units
19
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
6
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%2
100%70%0%0
100%10%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400063

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400063
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths3 yrs 1 mth
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2026Dec 2027
Concrete structure (RCC)70%100%
Units booked (free sale)33%54%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Deepali Darshan J. P. Nagar Co-Operative Housing Society Limited by Westin Sankalp Developers is a 19-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in August 2024 with possession due in December 2026. 2 units booked out of 6 units for sale. The concrete structure (RCC) is 70% complete.

Read full summary

Deepali Darshan J. P. Nagar Co-Operative Housing Society Limited is a BMC-sanctioned project by Westin Sankalp Developers in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800077319. It was launched in August 2024. It has 19 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 19 units, 6 are for sale and 13 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.

2 units booked out of 6 units for sale (33%). Since the July 2026 update, 2 more units have been booked.