Aasamanta Laxmi Narayan, Goregaon East

by Aasamanta Realty · Goregaon East, Mumbai 400063 · Map

Launched
May 20243 yrs 10 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
10 of 1191% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 11 units

Rehab12 units for existing members

Total 23 units. Rehab units are not for sale.

Project facts

1 BHK
1
2 BHK
9
3 BHK
10
Other units
3
Total units
23
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
11
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%10
100%100%0%10
100%80%0%9
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400063

Projects with 10–40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400063
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths2 yrs 9 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2028Dec 2026
Concrete structure (RCC)100%55%
Units booked (free sale)91%46%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Aasamanta Laxmi Narayan by Aasamanta Realty is a 23-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in May 2024 with possession due in March 2028. 10 units booked out of 11 units for sale. The concrete structure (RCC) is complete.

Read full summary

Aasamanta Laxmi Narayan is a BMC-sanctioned project by Aasamanta Realty in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800056447. It was launched in May 2024. It has 23 units in 1 building: 20 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 23 units, 11 are for sale and 12 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.

10 units booked out of 11 units for sale (91%).