Saan Symphony, Goregaon East
by Santosh Raosaheb Navle · Goregaon East, Mumbai 400063 · Map
- Launched
- Apr 20243 yrs 1 mth promised
- Possession (MahaRERA)
- May 2027Not extended
- Concrete structure
- 15%Mid-construction
- Booked (free sale)
- 0 of 10% · 16 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 1 unit
Rehab16 units for existing members
Total 17 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 16
- Other units
- 1
- Total units
- 17
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 1
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 15% | 0% | 0 | |
| 100% | 0% | 0% | 0 | |
| 100% | 0% | 0% | 0 | |
| 40% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400063
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 1 mth | 2 yrs 9 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | May 2027 | Dec 2026 |
| Concrete structure (RCC) | 15% | 80% |
| Units booked (free sale) | 0% | 74% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Samarth Nandadeep Heights, Goregaon East
- Aasamanta Laxmi Narayan, Goregaon East
- Anubhuti Sadan CHSL, Goregaon East
- Ashwin Heights, Goregaon East
- Vira One, Goregaon East
- Deepali Darshan J. P. Nagar Co-Operative Housing Society Limited, Goregaon East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Samarth Nandadeep Heights | March 2024 | October 2026 | 0% | – |
| Aasamanta Laxmi Narayan | May 2024 | March 2028 | 100% | 10 units booked out of 11 units for sale |
| Anubhuti Sadan CHSL | May 2024 | December 2027 | 40% | – |
| Ashwin Heights | May 2024 | December 2026 | 100% | 14 units booked out of 24 units for sale |
| Vira One | January 2024 | December 2026 | 90% | 25 units booked out of 28 units for sale |
| Deepali Darshan J. P. Nagar Co-Operative Housing Society Limited | August 2024 | December 2026 | 70% | 2 units booked out of 6 units for sale |
About this project
Saan Symphony by Santosh Raosaheb Navle is a 17-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in April 2024 with possession due in May 2027. 0 units booked out of 1 unit for sale. The concrete structure (RCC) is 15% complete.
Read full summary
Saan Symphony is a BMC-sanctioned project by Santosh Raosaheb Navle in Goregaon East, Mumbai 400063, registered with MahaRERA as P51900055723. It was launched in April 2024. It has 17 units in 1 building: 16 homes (1 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 17 units, 1 is for sale and 16 are rehab units for existing members.
Its registered possession date is May 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 15% complete, final finishes not started.
0 units booked out of 1 unit for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 15%.