Mohini Engineers And Contractors, Santacruz West

by Haris Gulabrai Chawla · Santacruz West, Mumbai 400054 · Map

Launched
Aug 20243 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
29
2 BHK
11
Other units
4
Total units
45
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400054

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths3 yrs
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2027May 2027
Concrete structure (RCC)0%75%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Mohini Engineers And Contractors by Haris Gulabrai Chawla is a 45-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in August 2024 with possession due in December 2027. Work on the concrete structure (RCC) has not started.

Read full summary

Mohini Engineers And Contractors is a BMC-sanctioned project by Haris Gulabrai Chawla in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800077503. It was launched in August 2024. It has 45 units in 1 building: 41 homes (1 RK, 1 BHK and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.