Seasons Prem Sagar, Santacruz West

Lapsed

by D S Enterprise · Santacruz West, Mumbai 400054 · Map

Launched
Dec 20241 yr promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked (free sale)
–No units for sale
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free saleNo units for sale

Rehab33 units for existing members

Land-owner share3 units, not for sale

Total 36 units. Rehab and land-owner units are not for sale.

Project facts

2 BHK
4
3 BHK
29
Other units
3
Total units
36
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
0
Rehab units
33
Land-owner share (not for sale)
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Oct 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 95%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%0%0%0
95%0%0%–
95%0%0%–
95%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400054

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr2 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2025Dec 2027
Concrete structure (RCC)0%62%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Seasons Prem Sagar by D S Enterprise is a 36-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in December 2024; its MahaRERA registration has lapsed. No units for sale: rehab and land-owner units only. Work on the concrete structure (RCC) has not started.

Read full summary

Seasons Prem Sagar is a BMC-sanctioned project by D S Enterprise in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800078579. It was launched in December 2024. It has 36 units in 1 building: 33 homes (2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 36 units, none is for sale, 33 are rehab units for existing members and 3 are the land-owner's share, not for sale.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation 95% complete, structure (RCC) not started, final finishes not started.

No units for sale: rehab and land-owner units only.