Skip to main content

92 Platinum Hive, Borivali West

by Parsh Realtors · Borivali West, Mumbai 400092 · Map

Launched
Nov 20244 yrs 1 mth promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
95%Mid-construction
Booked (free sale)
16 of 2176% · 54 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale16 booked out of 21 units

Rehab54 units for existing members

Total 75 units. Rehab units are not for sale.

Project facts

2 BHK
36
3 BHK
12
4 BHK
10
Other units
17
Total units
75
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
21
Rehab units
54

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 23%Jul 2026: Concrete structure (RCC) 63%Oct 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 95%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%16
100%63%0%11
100%23%0%11
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 1 mth3 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Jul 2028
Concrete structure (RCC)95%38%
Units booked (free sale)76%39%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

92 Platinum Hive by Parsh Realtors is a 75-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in November 2024 with possession due in December 2028. 16 units booked out of 21 units for sale. The concrete structure (RCC) is 95% complete.

Read full summary

92 Platinum Hive is a BMC-sanctioned project by Parsh Realtors in Borivali West, Mumbai 400092, registered with MahaRERA as P51800078001. It was launched in November 2024. It has 75 units in 1 building: 58 homes (2, 3 and 4 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 75 units, 21 are for sale and 54 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.

16 units booked out of 21 units for sale (76%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 63% to 95%.