Regent Kashi Kunj, Vile Parle East

by Regent Builders · Vile Parle East, Mumbai 400057 · Map

Launched
Oct 20243 yrs 5 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
14 of 2458% · 22 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 24 units

Rehab22 units for existing members

Total 46 units. Rehab units are not for sale.

Project facts

1 BHK
29
2 BHK
17
Total units
46
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
24
Rehab units
22

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 24%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%14
100%100%0%12
100%24%0%5
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths2 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2028Aug 2027
Concrete structure (RCC)100%100%
Units booked (free sale)58%51%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Regent Kashi Kunj by Regent Builders is a 46-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in October 2024 with possession due in March 2028. 14 units booked out of 24 units for sale. The concrete structure (RCC) is complete.

Read full summary

Regent Kashi Kunj is a BMC-sanctioned project by Regent Builders in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800077648. It was launched in October 2024. It has 46 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 24 are for sale and 22 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.

14 units booked out of 24 units for sale (58%). Since the July 2026 update, 2 more units have been booked.