Kush Heritage, Vile Parle East
by Kush Realty · Vile Parle East, Mumbai 400057 · Map
- Launched
- Nov 20242 yrs 7 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 8 of 2040% · 49 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale8 booked out of 20 units
Rehab49 units for existing members
Total 69 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 12
- 2 BHK
- 33
- 3 BHK
- 9
- Other units
- 15
- Total units
- 69
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 20
- Rehab units
- 49
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 8 | |
| 100% | 100% | 10% | 8 | |
| 100% | 40% | 0% | 2 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 7 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2027 | Mar 2028 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 40% | 51% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Zee Sadguru, Vile Parle East
- Pruthvi Mayur Park, Vile Parle East
- Regent Kashi Kunj, Vile Parle East
- Signature, Vile Parle East
- Kamla Arunkamal, Vile Parle East
- Zee Sai Chintan, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Zee Sadguru | November 2024 | December 2027 | 100% | 11 units booked out of 37 units for sale |
| Pruthvi Mayur Park | November 2024 | March 2028 | 100% | 8 units booked out of 10 units for sale |
| Regent Kashi Kunj | October 2024 | March 2028 | 100% | 14 units booked out of 24 units for sale |
| Signature | December 2024 | March 2028 | 100% | 42 units booked out of 42 units for sale |
| Kamla Arunkamal | January 2025 | December 2027 | 70% | 6 units booked out of 23 units for sale |
| Zee Sai Chintan | February 2025 | December 2028 | 100% | 13 units booked out of 30 units for sale |
About this project
Kush Heritage by Kush Realty is a 69-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in November 2024 with possession due in June 2027. 8 units booked out of 20 units for sale. The concrete structure (RCC) is complete.
Read full summary
Kush Heritage is a BMC-sanctioned project by Kush Realty in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800078232. It was launched in November 2024. It has 69 units in 1 building: 54 homes (1, 2 and 3 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 69 units, 20 are for sale and 49 are rehab units for existing members.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.
8 units booked out of 20 units for sale (40%).