Ekta Suprabhat C.H.S.L, Goregaon West
Ready to moveLapsed
by S D Construction · Goregaon West, Mumbai 400104 · Map
- Launched
- Nov 20241 yr 1 mth promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 20.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 93
- 2 BHK
- 44
- 3 BHK
- 2
- Other units
- 90
- Total units
- 229
- Buildings
- 2
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400104
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 1 mth | 3 yrs 10 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2025 | Jan 2029 |
| Concrete structure (RCC) | 100% | 51% |
| Units booked | – | 65% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Ashirwad Avenue, Goregaon West
- 38 Avenue, Goregaon West
- Ariha Skyes, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ashirwad Avenue | January 2025 | December 2028 | 100% | 51 units booked out of 78 units for sale |
| 38 Avenue | March 2025 | January 2029 | 6% | 28 units booked out of 72 units for sale |
| Ariha Skyes | May 2025 | March 2029 | 51% | 32 units booked out of 42 units for sale |
About this project
Ekta Suprabhat C.H.S.L by S D Construction is a 229-unit project in Goregaon West, Mumbai 400104, launched in November 2024; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Ekta Suprabhat C.H.S.L is a project by S D Construction in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800077847. It was launched in November 2024. It has 229 units in 2 buildings: 139 homes (1, 2 and 3 BHK) and 90 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.