Milestone, Kurla West
by Ojas Corporation · Kurla West, Mumbai 400070 · Map
- Launched
- Nov 20243 yrs 5 mths promised
- Possession (MahaRERA)
- Apr 2028Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 16 of 2662% · 21 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale16 booked out of 26 units
Rehab21 units for existing members
Total 47 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 17
- 2 BHK
- 15
- 3 BHK
- 7
- 4 BHK
- 1
- Other units
- 7
- Total units
- 47
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 26
- Rehab units
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 40% | 16 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400070
Projects with 20–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Apr 2028 | Dec 2027 |
| Concrete structure (RCC) | 100% | 45% |
| Units booked (free sale) | 62% | 33% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Urban Orion, Kurla West
- Rajal Happy Home, Kurla West
- Majestic Vista, Kurla West
- Manraj Residency, Kurla West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Urban Orion | December 2024 | December 2027 | 100% | 19 units booked out of 24 units for sale |
| Rajal Happy Home | March 2025 | December 2027 | 0% | 0 units booked out of 26 units for sale |
| Majestic Vista | March 2025 | June 2028 | 90% | 8 units booked out of 22 units for sale |
| Manraj Residency | May 2025 | December 2027 | 0% | 6 units booked out of 20 units for sale |
About this project
Milestone by Ojas Corporation is a 47-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in November 2024 with possession due in April 2028. 16 units booked out of 26 units for sale. The concrete structure (RCC) is complete.
Read full summary
Milestone is a BMC-sanctioned project by Ojas Corporation in Kurla West, Mumbai 400070, registered with MahaRERA as P51800078128. It was launched in November 2024. It has 47 units in 1 building: 40 homes (1, 2, 3 and 4 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 26 are for sale and 21 are rehab units for existing members.
Its registered possession date is April 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.
16 units booked out of 26 units for sale (62%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100%.