Urban Orion, Kurla West

Ready to move

by Associated Builders · Kurla West, Mumbai 400070 · Map

Launched
Dec 20243 yrs promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
19 of 2479% · 26 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale19 booked out of 24 units

Rehab26 units for existing members

Total 50 units. Rehab units are not for sale.

Project facts

1 RK
5
1 BHK
24
2 BHK
7
Other units
14
Total units
50
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
24
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%19
0%0%0%14
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400070

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400070
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2027Feb 2028
Concrete structure (RCC)100%45%
Units booked (free sale)79%33%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Urban Orion by Associated Builders is a 50-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in December 2024 with possession due in December 2027. 19 units booked out of 24 units for sale. The concrete structure (RCC) is complete.

Read full summary

Urban Orion is a BMC-sanctioned project by Associated Builders in Kurla West, Mumbai 400070, registered with MahaRERA as P51800078516. It was launched in December 2024. It has 50 units in 1 building: 36 homes (1 RK, 1 BHK and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 50 units, 24 are for sale and 26 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

19 units booked out of 24 units for sale (79%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.