Nidhaan Corporate Park, Ghatkopar East

by Nidhaan Properties LLP · Ghatkopar East, Mumbai 400077 · Map

Launched
Dec 20243 yrs promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
8 of 1197% · 24 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 119 units

Rehab24 units for existing members

Total 143 units. Rehab units are not for sale.

Project facts

1 RK
3
1 BHK
9
2 BHK
3
Other units
128
Total units
143
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
119
Rehab units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services35%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 35%Excavation 100%Concrete structure (RCC) 100%Final finishes 35%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%35%8
100%80%0%4
100%80%0%2
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400077

Projects with up to 30 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2027Jun 2028
Concrete structure (RCC)100%80%
Units booked (free sale)7%25%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Nidhaan Corporate Park by Nidhaan Properties LLP is a 143-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in December 2024 with possession due in December 2027. 8 units booked out of 119 units for sale. The concrete structure (RCC) is complete.

Read full summary

Nidhaan Corporate Park is a BMC-sanctioned project by Nidhaan Properties LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800078312. It was launched in December 2024. It has 143 units in 2 buildings: 15 homes (1 RK, 1 BHK and 2 BHK) and 128 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 143 units, 119 are for sale and 24 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 35% complete.

8 units booked out of 119 units for sale (7%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 80% to 100%.