Urban Frames, Ghatkopar East

by Aayushi Realtors LLP · Ghatkopar East, Mumbai 400077 · Map

Launched
Apr 20252 yrs 6 mths promised
Possession (MahaRERA)
Oct 2027Not extended
Concrete structure
92%Mid-construction
Booked (free sale)
1 of 215% · 3 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 21 units

Rehab3 units for existing members

Total 24 units. Rehab units are not for sale.

Project facts

2 BHK
15
3 BHK
8
5+ BHK
1
Total units
24
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
21
Rehab units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 36%Jul 2026: Concrete structure (RCC) 92%Oct 2026: Concrete structure (RCC) 92%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 92%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%20%1
100%92%0%0
100%36%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400077

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 6 mths2 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Oct 2027Jan 2028
Concrete structure (RCC)92%65%
Units booked (free sale)5%13%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Urban Frames by Aayushi Realtors LLP is a 24-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in April 2025 with possession due in October 2027. 1 unit booked out of 21 units for sale. The concrete structure (RCC) is 92% complete.

Read full summary

Urban Frames is a BMC-sanctioned project by Aayushi Realtors LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800080065. It was launched in April 2025. It has 24 units in 1 building, with 2, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 24 units, 21 are for sale and 3 are rehab units for existing members.

Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 92% complete, final finishes 20% complete.

1 unit booked out of 21 units for sale (5%). Since the July 2026 update, 1 more unit has been booked.