Vardhaman Palace, Ghatkopar East
by Vardhaman Infra Construction Limited · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Dec 20253 yrs promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 1 of 425% · 18 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 4 units
Rehab18 units for existing members
Total 22 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 1
- 3 BHK
- 14
- Other units
- 7
- Total units
- 22
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 4
- Rehab units
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 85% | 1 | |
| 100% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400077
Projects with up to 30 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs | 3 yrs |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2028 | Mar 2028 |
| Concrete structure (RCC) | 80% | 60% |
| Units booked (free sale) | 25% | 7% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Ghatkopar Tribhuvan Chsl, Ghatkopar East
- Ghatkopar Virat CHSL, Ghatkopar East
- Nidhaan Corporate Park, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ghatkopar Tribhuvan Chsl | November 2025 | March 2028 | 60% | 1 unit booked out of 1 unit for sale |
| Ghatkopar Virat CHSL | April 2026 | December 2029 | 0% | 0 units booked out of 8 units for sale |
| Nidhaan Corporate Park | December 2024 | December 2027 | 100% | 8 units booked out of 119 units for sale |
About this project
Vardhaman Palace by Vardhaman Infra Construction Limited is a 22-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in December 2025 with possession due in December 2028. 1 unit booked out of 4 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Vardhaman Palace is a BMC-sanctioned project by Vardhaman Infra Construction Limited in Ghatkopar East, Mumbai 400077, registered with MahaRERA as PM1180002501694. It was launched in December 2025. It has 22 units in 1 building: 15 homes (2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 22 units, 4 are for sale and 18 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes 85% complete.
1 unit booked out of 4 units for sale (25%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 80%.