Sheetal Shashanka, Borivali West
by D.G.S Land Developers (India) Private Limited · Borivali West, Mumbai 400091 · Map
- Launched
- Dec 20245 yrs promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 106 of 19155% · 55 rehab units
- Buildings
- 30.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale106 booked out of 191 units
Rehab55 units for existing members
Total 246 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 110
- 2 BHK
- 135
- Other units
- 1
- Total units
- 246
- Buildings
- 3
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 191
- Rehab units
- 55
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 0% | 106 | |
| 100% | 83% | 0% | 106 | |
| 76% | 10% | 0% | 106 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400091
Projects with 100–500 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs | 4 yrs 9 mths |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Dec 2029 | Mar 2029 |
| Concrete structure (RCC) | 95% | 95% |
| Units booked (free sale) | 55% | 84% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Avyukta Vedant, Borivali West
- Breeze 91, Borivali West
- Rashmi Square, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Avyukta Vedant | June 2024 | March 2029 | 95% | 65 units booked out of 79 units for sale |
| Breeze 91 | June 2025 | March 2030 | 65% | 54 units booked out of 61 units for sale |
| Rashmi Square | February 2024 | May 2027 | 100% | 62 units booked out of 74 units for sale |
About this project
Sheetal Shashanka by D.G.S Land Developers (India) Private Limited is a 246-unit SRA-sanctioned project in Borivali West, Mumbai 400091, launched in December 2024 with possession due in December 2029. 106 units booked out of 191 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Sheetal Shashanka is an SRA-sanctioned project by D.G.S Land Developers (India) Private Limited in Borivali West, Mumbai 400091, registered with MahaRERA as P51800078320. It was launched in December 2024. It has 246 units in 3 buildings: 245 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 246 units, 191 are for sale and 55 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.
106 units booked out of 191 units for sale (55%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 83% to 95%.