Breeze 91, Borivali West

by Kaustubh Construction Private Limited · Borivali West, Mumbai 400091 · Map

Launched
Jun 20254 yrs 9 mths promised
Possession (MahaRERA)
Mar 2030Not extended
Concrete structure
65%Mid-construction
Booked (free sale)
54 of 6189% · 57 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale54 booked out of 61 units

Rehab57 units for existing members

Total 118 units. Rehab units are not for sale.

Project facts

1 BHK
3
2 BHK
36
3 BHK
75
5+ BHK
1
Other units
3
Total units
118
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
61
Rehab units
57

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)65%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 15%Oct 2026: Concrete structure (RCC) 65%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 65%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%65%0%54
100%15%0%52
100%0%0%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400091

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400091
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 9 mths3 yrs 9 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Mar 2030Mar 2029
Concrete structure (RCC)65%25%
Units booked (free sale)89%55%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Breeze 91 by Kaustubh Construction Private Limited is a 118-unit MHADA-sanctioned project in Borivali West, Mumbai 400091, launched in June 2025 with possession due in March 2030. 54 units booked out of 61 units for sale. The concrete structure (RCC) is 65% complete.

Read full summary

Breeze 91 is a MHADA-sanctioned project by Kaustubh Construction Private Limited in Borivali West, Mumbai 400091, registered with MahaRERA as P51800080406. It was launched in June 2025. It has 118 units in 1 building: 115 homes (1, 2, 3 and 5+ BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 118 units, 61 are for sale and 57 are rehab units for existing members.

Its registered possession date is March 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 65% complete, final finishes not started.

54 units booked out of 61 units for sale (89%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 15% to 65%.