Signature, Vile Parle East

by Mangal Buildhome Private Limited · Vile Parle East, Mumbai 400057 · Map

Launched
Dec 20243 yrs 3 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
42 of 42100% · 82 rehab units
Buildings
20.7 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale42 booked out of 42 units

Rehab82 units for existing members

Total 124 units. Rehab units are not for sale.

Project facts

1 RK
7
1 BHK
27
2 BHK
40
3 BHK
17
4 BHK
8
5+ BHK
3
Other units
22
Total units
124
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
1
Free-sale units
42
Rehab units
82
Reserved units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 35%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 100%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%42
100%35%0%24
100%0%0%24
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths3 yrs
Possession date extendedNo1 of 6
Possession date (MahaRERA)Mar 2028Dec 2027
Concrete structure (RCC)100%85%
Units booked (free sale)100%30%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Signature by Mangal Buildhome Private Limited is a 124-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in December 2024 with possession due in March 2028. 42 units booked out of 42 units for sale. The concrete structure (RCC) is complete.

Read full summary

Signature is a BMC-sanctioned project by Mangal Buildhome Private Limited in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800078445. It was launched in December 2024. It has 124 units in 2 buildings: 102 homes (1 RK, 1 BHK, 2 BHK, 3 BHK, 4 BHK and 5+ BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 124 units, 42 are for sale and 82 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 20% complete.

42 units booked out of 42 units for sale (100%). Since the July 2026 update, 18 more units have been booked and the reported concrete structure (RCC) has gone from 35% to 100%.