Skip to main content

Zee Sai Chintan, Vile Parle East

Ready to move

by MPR Builders and Developers LLP · Vile Parle East, Mumbai 400057 · Map

Launched
Feb 20253 yrs 10 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Ready to move
Booked (free sale)
13 of 3043% · 34 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 30 units

Rehab34 units for existing members

Total 64 units. Rehab units are not for sale.

Project facts

1 BHK
12
2 BHK
26
3 BHK
21
Other units
5
Total units
64
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
30
Rehab units
34

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 98%Jul 2026: Excavation 98%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%13
98%100%0%8
98%25%0%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths2 yrs 9 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Sep 2027
Concrete structure (RCC)100%85%
Units booked (free sale)43%30%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Zee Sai Chintan by MPR Builders and Developers LLP is a 64-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in February 2025 with possession due in December 2028. 13 units booked out of 30 units for sale. The concrete structure (RCC) is complete.

Read full summary

Zee Sai Chintan is a BMC-sanctioned project by MPR Builders and Developers LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800079226. It was launched in February 2025. It has 64 units in 1 building: 59 homes (1, 2 and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 64 units, 30 are for sale and 34 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

13 units booked out of 30 units for sale (43%). Since the July 2026 update, 5 more units have been booked.