Rashmi Manorath, Borivali East

by Modi's Navnirman Limited · Borivali East, Mumbai 400066 · Map

Launched
Dec 20241 yr 8 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 1 yr 4 mths
Concrete structure
95%Mid-construction
Booked (free sale)
11 of 3829% · 49 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale11 booked out of 38 units

Rehab49 units for existing members

Total 87 units. Rehab units are not for sale.

Project facts

1 BHK
24
2 BHK
59
3 BHK
4
Total units
87
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
38
Rehab units
49

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 20%Jul 2026: Concrete structure (RCC) 53%Oct 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 15%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 95%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%50%11
100%53%15%3
100%20%0%3
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 8 mths3 yrs 2 mths
Possession date extendedBy 1 yr 4 mths0 of 6
Possession date (MahaRERA)Dec 2027Dec 2027
Concrete structure (RCC)95%90%
Units booked (free sale)29%47%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Rashmi Manorath by Modi's Navnirman Limited is an 87-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in December 2024 with possession due in December 2027. 11 units booked out of 38 units for sale. The concrete structure (RCC) is 95% complete.

Read full summary

Rashmi Manorath is a BMC-sanctioned project by Modi's Navnirman Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800078598. It was launched in December 2024. It has 87 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 87 units, 38 are for sale and 49 are rehab units for existing members.

Its registered possession date is December 2027, extended by 1 year 4 months from the original August 2026. Construction: excavation complete, structure (RCC) 95% complete, final finishes 50% complete.

11 units booked out of 38 units for sale (29%). Since the July 2026 update, 8 more units have been booked, the reported concrete structure (RCC) has gone from 53% to 95% and the possession date has moved from August 2026 to December 2027.