Rashmi Manorath, Borivali East
by Modi's Navnirman Limited · Borivali East, Mumbai 400066 · Map
- Launched
- Dec 20241 yr 8 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr 4 mths
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 11 of 3829% · 49 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale11 booked out of 38 units
Rehab49 units for existing members
Total 87 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 24
- 2 BHK
- 59
- 3 BHK
- 4
- Total units
- 87
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 38
- Rehab units
- 49
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 50% | 11 | |
| 100% | 53% | 15% | 3 | |
| 100% | 20% | 0% | 3 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400066
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 8 mths | 3 yrs 2 mths |
| Possession date extended | By 1 yr 4 mths | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2027 |
| Concrete structure (RCC) | 95% | 90% |
| Units booked (free sale) | 29% | 47% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Rajdeep Co-Operative Housing Society Ltd, Borivali East
- Rajendra Nagar Omsai Co-Operative Housing Society Limited, Borivali East
- Swanand Co-Operative Housing Society Limited, Borivali East
- Nl Park View, Borivali East
- Borivali Shiv Sadan CHSL, Borivali East
- Nirala Opal, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rajdeep Co-Operative Housing Society Ltd | December 2024 | December 2027 | 80% | 20 units booked out of 36 units for sale |
| Rajendra Nagar Omsai Co-Operative Housing Society Limited | January 2025 | December 2027 | 100% | 1 unit booked out of 22 units for sale |
| Swanand Co-Operative Housing Society Limited | March 2025 | December 2027 | 70% | 11 units booked out of 28 units for sale |
| Nl Park View | August 2024 | May 2028 | 100% | 34 units booked out of 41 units for sale |
| Borivali Shiv Sadan CHSL | June 2024 | October 2027 | 100% | 65 units booked out of 66 units for sale |
| Nirala Opal | July 2025 | June 2029 | 35% | 0 units booked out of total 120 units |
About this project
Rashmi Manorath by Modi's Navnirman Limited is an 87-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in December 2024 with possession due in December 2027. 11 units booked out of 38 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Rashmi Manorath is a BMC-sanctioned project by Modi's Navnirman Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800078598. It was launched in December 2024. It has 87 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 87 units, 38 are for sale and 49 are rehab units for existing members.
Its registered possession date is December 2027, extended by 1 year 4 months from the original August 2026. Construction: excavation complete, structure (RCC) 95% complete, final finishes 50% complete.
11 units booked out of 38 units for sale (29%). Since the July 2026 update, 8 more units have been booked, the reported concrete structure (RCC) has gone from 53% to 95% and the possession date has moved from August 2026 to December 2027.