Nl Park View, Borivali East
Ready to move
by Beautiful Properties Private Limited · Borivali East, Mumbai 400066 · Map
- Launched
- Aug 20243 yrs 9 mths promised
- Possession (MahaRERA)
- May 2028Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 34 of 4183% · 37 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale34 booked out of 41 units
Rehab37 units for existing members
Total 78 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 14
- 2 BHK
- 56
- Other units
- 8
- Total units
- 78
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 41
- Rehab units
- 37
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 34 | |
| 100% | 90% | 0% | 32 | |
| 100% | 70% | 0% | 33 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400066
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs 2 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | May 2028 | Dec 2027 |
| Concrete structure (RCC) | 100% | 60% |
| Units booked (free sale) | 83% | 49% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Trilok Giriraj Kripa, Borivali East
- Borivali Shiv Sadan CHSL, Borivali East
- Shiv Krupa, Borivali East
- Rajdeep Co-Operative Housing Society Ltd, Borivali East
- Rashmi Manorath, Borivali East
- Anand Co-Operative Housing Society Ltd Building No 2, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Trilok Giriraj Kripa | August 2024 | July 2028 | 40% | – |
| Borivali Shiv Sadan CHSL | June 2024 | October 2027 | 100% | 65 units booked out of 66 units for sale |
| Shiv Krupa | May 2024 | December 2028 | 25% | 39 units booked out of 80 units for sale |
| Rajdeep Co-Operative Housing Society Ltd | December 2024 | December 2027 | 80% | 20 units booked out of 36 units for sale |
| Rashmi Manorath | December 2024 | December 2027 | 95% | 11 units booked out of 38 units for sale |
| Anand Co-Operative Housing Society Ltd Building No 2 | April 2024 | December 2026 | 38% | 15 units booked out of 41 units for sale |
About this project
Nl Park View by Beautiful Properties Private Limited is a 78-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in August 2024 with possession due in May 2028. 34 units booked out of 41 units for sale. The concrete structure (RCC) is complete.
Read full summary
Nl Park View is a BMC-sanctioned project by Beautiful Properties Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800077375. It was launched in August 2024. It has 78 units in 1 building: 70 homes (1 and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 78 units, 41 are for sale and 37 are rehab units for existing members.
Its registered possession date is May 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
34 units booked out of 41 units for sale (83%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 90% to 100%.