Borivali Shiv Sadan CHSL, Borivali East

by Ossia developers · Borivali East, Mumbai 400066 · Map

Launched
Jun 20243 yrs 4 mths promised
Possession (MahaRERA)
Oct 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
65 of 6698% · 62 rehab units
Buildings
20.6 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale65 booked out of 66 units

Rehab62 units for existing members

Total 128 units. Rehab units are not for sale.

Project facts

1 BHK
50
2 BHK
72
Other units
6
Total units
128
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
1
Free-sale units
66
Rehab units
62

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 16%Dec 2025: Concrete structure (RCC) 16%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%65
100%100%0%57
100%16%0%38
100%16%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths3 yrs
Possession date extendedNo1 of 6
Possession date (MahaRERA)Oct 2027Sep 2027
Concrete structure (RCC)100%66%
Units booked (free sale)98%43%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Borivali Shiv Sadan CHSL by Ossia developers is a 128-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in June 2024 with possession due in October 2027. 65 units booked out of 66 units for sale. The concrete structure (RCC) is complete.

Read full summary

Borivali Shiv Sadan CHSL is a BMC-sanctioned project by Ossia developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800066573. It was launched in June 2024. It has 128 units in 2 buildings: 122 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 128 units, 66 are for sale and 62 are rehab units for existing members.

Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.

65 units booked out of 66 units for sale (98%). Since the July 2026 update, 8 more units have been booked.