Sagar Manthan, Kandivali West
by Bhoomi Associates · Kandivali West, Mumbai 400067 · Map
- Launched
- Dec 20242 yrs 9 mths promised
- Possession (MahaRERA)
- Sep 2027Not extended
- Concrete structure
- 61%Mid-construction
- Booked (free sale)
- 23 of 3664% · 21 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale23 booked out of 36 units
Rehab21 units for existing members
Total 57 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 38
- 3 BHK
- 15
- Other units
- 4
- Total units
- 57
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 36
- Rehab units
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 61% | 0% | 23 | |
| 100% | 21% | 0% | 15 | |
| 100% | 9% | 0% | 13 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Sep 2027 | Dec 2027 |
| Concrete structure (RCC) | 61% | 38% |
| Units booked (free sale) | 64% | 42% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Ambit Primoris, Kandivali West
- Alok, Kandivali West
- Om Shri Ganesh CHS LTD, Kandivali West
- Center Point, Kandivali West
- Aashray, Kandivali West
- Swastik House - C Wing, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ambit Primoris | January 2025 | December 2027 | 0% | 164 units booked out of total 183 units |
| Alok | October 2024 | September 2026 | 100% | 6 units booked out of 23 units for sale |
| Om Shri Ganesh CHS LTD | March 2025 | December 2026 | 100% | 17 units booked out of total 29 units |
| Center Point | August 2024 | December 2027 | 10% | – |
| Aashray | April 2025 | December 2027 | 35% | 0 units booked out of 7 units for sale |
| Swastik House - C Wing | August 2024 | March 2030 | 40% | – |
About this project
Sagar Manthan by Bhoomi Associates is a 57-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in December 2024 with possession due in September 2027. 23 units booked out of 36 units for sale. The concrete structure (RCC) is 61% complete.
Read full summary
Sagar Manthan is a MHADA-sanctioned project by Bhoomi Associates in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800078613. It was launched in December 2024. It has 57 units in 1 building: 53 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 57 units, 36 are for sale and 21 are rehab units for existing members.
Its registered possession date is September 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 61% complete, final finishes not started.
23 units booked out of 36 units for sale (64%). Since the July 2026 update, 8 more units have been booked and the reported concrete structure (RCC) has gone from 21% to 61%.