Om Shri Ganesh CHS LTD, Kandivali West

Ready to move

by Vardhman 9 Square LLP · Kandivali West, Mumbai 400067 · Map

Launched
Mar 20251 yr 9 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Ready to move
Booked
17 of 2959% · 13 in Jul 2026
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
27
Other units
2
Total units
29
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 5%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 10%Jul 2026: Final finishes 75%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%17
100%100%75%13
5%0%10%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 9 mths2 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2026Dec 2027
Concrete structure (RCC)100%57%
Units booked59%38%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Om Shri Ganesh CHS LTD by Vardhman 9 Square LLP is a 29-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in March 2025 with possession due in December 2026. 17 units booked out of total 29 units. The concrete structure (RCC) is complete.

Read full summary

Om Shri Ganesh CHS LTD is a BMC-sanctioned project by Vardhman 9 Square LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800079561. It was launched in March 2025. It has 29 units in 1 building: 27 homes (1 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

17 units booked out of total 29 units (59%). Since the July 2026 update, 4 more units have been booked.