Aashray, Kandivali West
by Creative Builders · Kandivali West, Mumbai 400067 · Map
- Launched
- Apr 20252 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 35%Mid-construction
- Booked (free sale)
- 0 of 70% · 29 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 7 units
Rehab29 units for existing members
Total 36 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 20
- 2 BHK
- 9
- Other units
- 7
- Total units
- 36
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 7
- Rehab units
- 29
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 5% | 0 | |
| 95% | 5% | 0% | 0 | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 2 yrs 9 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Jan 2028 |
| Concrete structure (RCC) | 35% | 57% |
| Units booked (free sale) | 0% | 46% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Om Shri Ganesh CHS LTD, Kandivali West
- Mpr Shri Paras Darshan, Kandivali West
- Vencon Bhagat Niwas, Kandivali West
- Triratna, Kandivali West
- Sagar Manthan, Kandivali West
- West Center Meridian Court, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Om Shri Ganesh CHS LTD | March 2025 | December 2026 | 100% | 17 units booked out of total 29 units |
| Mpr Shri Paras Darshan | May 2025 | February 2028 | 53% | 10 units booked out of 25 units for sale |
| Vencon Bhagat Niwas | May 2025 | December 2027 | 63% | 13 units booked out of 39 units for sale |
| Triratna | May 2025 | June 2028 | 27% | 14 units booked out of 38 units for sale |
| Sagar Manthan | December 2024 | September 2027 | 61% | 23 units booked out of 36 units for sale |
| West Center Meridian Court | September 2025 | December 2030 | 0% | 18 units booked out of total 34 units |
About this project
Aashray by Creative Builders is a 36-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in April 2025 with possession due in December 2027. 0 units booked out of 7 units for sale. The concrete structure (RCC) is 35% complete.
Read full summary
Aashray is a BMC-sanctioned project by Creative Builders in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800079965. It was launched in April 2025. It has 36 units in 1 building: 29 homes (1 and 2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 7 are for sale and 29 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 35% complete, final finishes 5% complete.
0 units booked out of 7 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 5% to 35%.