Shanti, Vile Parle East
by S.K. Realtors · Vile Parle East, Mumbai 400057 · Map
- Launched
- Jan 20252 yrs 6 mths promised
- Possession (MahaRERA)
- Jul 2027Not extended
- Concrete structure
- 27%Mid-construction
- Booked (free sale)
- 5 of 1145% · 7 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 11 units
Rehab7 units for existing members
Land-owner share6 units, not for sale
Total 24 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 3
- 2 BHK
- 7
- 3 BHK
- 10
- Other units
- 4
- Total units
- 24
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 11
- Rehab units
- 7
- Land-owner share (not for sale)
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 5% | 27% | 0% | 5 | |
| 5% | 22% | 0% | 4 | |
| 5% | 12% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400057
Projects with 10–40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 6 mths | 2 yrs 9 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Jul 2027 | Aug 2027 |
| Concrete structure (RCC) | 27% | 85% |
| Units booked (free sale) | 45% | 48% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Rakyan Imperia, Vile Parle East
- Goyal Atlantis, Vile Parle East
- Sadasukh, Vile Parle East
- Pruthvi Mayur Park, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rakyan Imperia | November 2024 | September 2027 | 100% | 18 units booked out of 21 units for sale |
| Goyal Atlantis | November 2024 | July 2027 | 40% | 2 units booked out of 12 units for sale |
| Sadasukh | March 2025 | March 2027 | 70% | 1 unit booked out of 15 units for sale |
| Pruthvi Mayur Park | November 2024 | March 2028 | 100% | 8 units booked out of 10 units for sale |
About this project
Shanti by S.K. Realtors is a 24-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in January 2025 with possession due in July 2027. 5 units booked out of 11 units for sale. The concrete structure (RCC) is 27% complete.
Read full summary
Shanti is a BMC-sanctioned project by S.K. Realtors in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800078998. It was launched in January 2025. It has 24 units in 1 building: 20 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 24 units, 11 are for sale, 7 are rehab units for existing members and 6 are the land-owner's share, not for sale.
Its registered possession date is July 2027, unchanged since launch. Construction: excavation 5% complete, structure (RCC) 27% complete, final finishes not started.
5 units booked out of 11 units for sale (45%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 22% to 27%.