Sadasukh, Vile Parle East
by Shree Vighnaharta Lifespace LLP · Vile Parle East, Mumbai 400057 · Map
- Launched
- Mar 20252 yrs promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 1 of 157% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 15 units
Rehab16 units for existing members
Total 31 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 8
- 2 BHK
- 13
- 3 BHK
- 4
- 4 BHK
- 1
- Other units
- 5
- Total units
- 31
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 15
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 1 | |
| 100% | 70% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs | 3 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Mar 2027 | May 2028 |
| Concrete structure (RCC) | 70% | 78% |
| Units booked (free sale) | 7% | 44% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Pruthvi Ashakiran, Vile Parle East
- Siddhi Elite, Vile Parle East
- Zee Sai Chintan, Vile Parle East
- Shanti, Vile Parle East
- Vijayraj Dhavalganga, Vile Parle East
- Regent Priyadarshani, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pruthvi Ashakiran | April 2025 | August 2028 | 90% | 8 units booked out of 10 units for sale |
| Siddhi Elite | April 2025 | December 2026 | 50% | 0 units booked out of 12 units for sale |
| Zee Sai Chintan | February 2025 | December 2028 | 100% | 13 units booked out of 30 units for sale |
| Shanti | January 2025 | July 2027 | 27% | 5 units booked out of 11 units for sale |
| Vijayraj Dhavalganga | August 2025 | March 2028 | 90% | 18 units booked out of 19 units for sale |
| Regent Priyadarshani | September 2025 | March 2029 | 67% | 2 units booked out of 9 units for sale |
About this project
Sadasukh by Shree Vighnaharta Lifespace LLP is a 31-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in March 2025 with possession due in March 2027. 1 unit booked out of 15 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
Sadasukh is a BMC-sanctioned project by Shree Vighnaharta Lifespace LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800079774. It was launched in March 2025. It has 31 units in 1 building: 26 homes (1, 2, 3 and 4 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 15 are for sale and 16 are rehab units for existing members.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
1 unit booked out of 15 units for sale (7%). Since the July 2026 update, 1 more unit has been booked.