High Pavilion, Vikhroli

by Agastya Infra · Vikhroli, Mumbai 400083 · Map

Launched
Mar 20252 yrs 5 mths promised
Possession (MahaRERA)
Aug 2027Not extended
Concrete structure
79%Mid-construction
Booked
–
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
58
2 BHK
87
Total units
145
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)79%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 79%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 79%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%79%0%–
0%0%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400083

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths3 yrs 4 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Aug 2027Oct 2028
Concrete structure (RCC)79%43%
Units booked–73%
MahaRERA complaints (filed by or against the builder)01

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

High Pavilion by Agastya Infra is a 145-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in March 2025 with possession due in August 2027. The concrete structure (RCC) is 79% complete.

Read full summary

High Pavilion is a MHADA-sanctioned project by Agastya Infra in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800079411. It was launched in March 2025. It has 145 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 79% complete, final finishes not started.

Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 79%.