Skip to main content

Adityaraj Tapovan, Vikhroli

by Adityaraj Buildcon · Vikhroli, Mumbai 400083 · Map

Launched
Mar 20253 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
54%Mid-construction
Booked (free sale)
87 of 11973% · 33 rehab units
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale87 booked out of 119 units

Rehab33 units for existing members

Total 152 units. Rehab units are not for sale.

Project facts

1 BHK
144
Other units
8
Total units
152
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
119
Rehab units
33

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)54%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 33%Oct 2026: Concrete structure (RCC) 54%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 54%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%54%0%87
100%33%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400083

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths2 yrs 10 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2028Dec 2027
Concrete structure (RCC)54%43%
Units booked (free sale)73%75%
MahaRERA complaints (filed by or against the builder)10

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Adityaraj Tapovan by Adityaraj Buildcon is a 152-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in March 2025 with possession due in December 2028. 87 units booked out of 119 units for sale. The concrete structure (RCC) is 54% complete.

Read full summary

Adityaraj Tapovan is a MHADA-sanctioned project by Adityaraj Buildcon in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800079509. It was launched in March 2025. It has 152 units in 1 building: 144 homes (1 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 152 units, 119 are for sale and 33 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 54% complete, final finishes not started.

87 units booked out of 119 units for sale (73%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 33% to 54%.

Adityaraj's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA29
Total units across these projects3,149
Completed without extending the possession date7
Completed after an extension2
Lapsed10
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure3 years 6 months
MahaRERA complaints (filed by or against the builder), all Adityaraj projects2 (2 of 29 projects)

See all Adityaraj projects →