Adityaraj Tapovan, Vikhroli
by Adityaraj Buildcon · Vikhroli, Mumbai 400083 · Map
- Launched
- Mar 20253 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 54%Mid-construction
- Booked (free sale)
- 87 of 11973% · 33 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale87 booked out of 119 units
Rehab33 units for existing members
Total 152 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 144
- Other units
- 8
- Total units
- 152
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 119
- Rehab units
- 33
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 54% | 0% | 87 | |
| 100% | 33% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400083
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 2 yrs 10 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Dec 2028 | Dec 2027 |
| Concrete structure (RCC) | 54% | 43% |
| Units booked (free sale) | 73% | 75% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 5 projects
- High Pavilion, Vikhroli
- Truearth VEDAA, Vikhroli
- Mansarovar Residency, Vikhroli
- Unique Fortune, Vikhroli
- Adityaraj Pavilion, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| High Pavilion | March 2025 | August 2027 | 79% | – |
| Truearth VEDAA | April 2025 | December 2027 | 65% | 91 units booked out of 98 units for sale |
| Mansarovar Residency | February 2025 | December 2027 | 40% | 37 units booked out of 60 units for sale |
| Unique Fortune | June 2025 | October 2028 | 43% | 82 units booked out of 93 units for sale |
| Adityaraj Pavilion | August 2025 | December 2029 | 4% | 48 units booked out of 116 units for sale |
About this project
Adityaraj Tapovan by Adityaraj Buildcon is a 152-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in March 2025 with possession due in December 2028. 87 units booked out of 119 units for sale. The concrete structure (RCC) is 54% complete.
Read full summary
Adityaraj Tapovan is a MHADA-sanctioned project by Adityaraj Buildcon in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800079509. It was launched in March 2025. It has 152 units in 1 building: 144 homes (1 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 152 units, 119 are for sale and 33 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 54% complete, final finishes not started.
87 units booked out of 119 units for sale (73%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 33% to 54%.
Adityaraj's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 29 |
|---|---|
| Total units across these projects | 3,149 |
| Completed without extending the possession date | 7 |
| Completed after an extension | 2 |
| Lapsed | 10 |
| Under construction | 10 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 3 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Adityaraj projects | 2 (2 of 29 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.