Skip to main content

Raghav Serenity, Bandra East

by Raghav Raj Builders & Developers LLP · Bandra East, Mumbai 400051 · Map

Launched
Mar 20253 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
35%Mid-construction
Booked (free sale)
6 of 1046% · 42 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale6 booked out of 104 units

Rehab42 units for existing members

Total 146 units. Rehab units are not for sale.

Project facts

2 BHK
65
Other units
81
Total units
146
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
104
Rehab units
42

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)35%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 50%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 35%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 35%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%35%0%6
50%0%0%2
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400051

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400051
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths4 yrs 9 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2028Jun 2030
Concrete structure (RCC)35%0%
Units booked (free sale)6%17%
MahaRERA complaints (filed by or against the builder)01

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Raghav Serenity by Raghav Raj Builders & Developers LLP is a 146-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in March 2025 with possession due in December 2028. 6 units booked out of 104 units for sale. The concrete structure (RCC) is 35% complete.

Read full summary

Raghav Serenity is a MHADA-sanctioned project by Raghav Raj Builders & Developers LLP in Bandra East, Mumbai 400051, registered with MahaRERA as P51800079550. It was launched in March 2025. It has 146 units in 2 buildings: 65 homes (2 BHK) and 81 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 146 units, 104 are for sale and 42 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.

6 units booked out of 104 units for sale (6%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 35%.