Artek Park, Bandra East

by Arhan Homes LLP · Bandra East, Mumbai 400051 · Map

Launched
Sep 20254 yrs 9 mths promised
Possession (MahaRERA)
Jun 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
25 of 7334% · 54 rehab units
Buildings
31.8 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale25 booked out of 73 units

Rehab54 units for existing members

Total 127 units. Rehab units are not for sale.

Project facts

3 BHK
77
4 BHK
48
Other units
2
Total units
127
Buildings
3
Land
1.8 acres
Phases
1
MahaRERA complaints
1
Free-sale units
73
Rehab units
54

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%25
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400051

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400051
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 9 mths4 yrs 8 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Jun 2030Nov 2029
Concrete structure (RCC)0%0%
Units booked (free sale)34%6%
MahaRERA complaints (filed by or against the builder)10

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Artek Park by Arhan Homes LLP is a 127-unit BMC-sanctioned project in Bandra East, Mumbai 400051, launched in September 2025 with possession due in June 2030. 25 units booked out of 73 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Artek Park is a BMC-sanctioned project by Arhan Homes LLP in Bandra East, Mumbai 400051, registered with MahaRERA as PR1180002500855. It was launched in September 2025. It has 127 units in 3 buildings: 125 homes (3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 127 units, 73 are for sale and 54 are rehab units for existing members.

Its registered possession date is June 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

25 units booked out of 73 units for sale (34%). Since the July 2026 update, 25 more units have been booked.