Rustomjee Prive, Bandra East

by Keysky Realtors Private Limited · Bandra East, Mumbai 400051 · Map

Launched
Mar 20254 yrs 8 mths promised
Possession (MahaRERA)
Nov 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
36 of 5664% · 16 rehab units
Buildings
30.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale36 booked out of 56 units

Rehab16 units for existing members

Land-owner share10 units, not for sale

Total 82 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
2
2 BHK
11
3 BHK
69
Total units
82
Buildings
3
Land
0.5 acres
Phases
1
MahaRERA complaints
1
Free-sale units
56
Rehab units
16
Land-owner share (not for sale)
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%36
100%0%0%33
0%0%0%19

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400051

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400051
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 8 mths4 yrs 9 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Nov 2029Jun 2030
Concrete structure (RCC)0%0%
Units booked (free sale)64%6%
MahaRERA complaints (filed by or against the builder)10

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Rustomjee Prive by Keysky Realtors Private Limited (Rustomjee) is an 82-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in March 2025 with possession due in November 2029. 36 units booked out of 56 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Rustomjee Prive is a MHADA-sanctioned project by Keysky Realtors Private Limited in Bandra East, Mumbai 400051, registered with MahaRERA as P51800079537. It was launched in March 2025. It has 82 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 82 units, 56 are for sale, 16 are rehab units for existing members and 10 are the land-owner's share, not for sale.

Its registered possession date is November 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

36 units booked out of 56 units for sale (64%). Since the July 2026 update, 3 more units have been booked.

Rustomjee's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA38
Total units across these projects3,435
Completed without extending the possession date15
Completed after an extension2
Lapsed5
Under construction16
Possession date extended on the builder's application8
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Rustomjee projects119 (11 of 38 projects)

See all Rustomjee projects →