Skip to main content

Anvaya, Kandivali West

by Gagangiri Gargi Construction · Kandivali West, Mumbai 400067 · Map

Launched
Jun 20254 yrs 11 mths promised
Possession (MahaRERA)
May 2030Not extended
Concrete structure
14%Mid-construction
Booked (free sale)
31 of 7044% · 26 rehab units
Buildings
1373.7 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale31 booked out of 70 units

Rehab26 units for existing members

Total 96 units. Rehab units are not for sale.

Project facts

1 BHK
17
2 BHK
38
3 BHK
31
4 BHK
1
Other units
9
Total units
96
Buildings
1
Land
373.7 acres
Phases
1
MahaRERA complaints
1
Free-sale units
70
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)14%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 14%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 14%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%14%0%31
100%0%0%16
100%0%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths3 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)May 2030Nov 2028
Concrete structure (RCC)14%38%
Units booked (free sale)44%35%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Anvaya by Gagangiri Gargi Construction is a 96-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in June 2025 with possession due in May 2030. 31 units booked out of 70 units for sale. The concrete structure (RCC) is 14% complete.

Read full summary

Anvaya is a MHADA-sanctioned project by Gagangiri Gargi Construction in Kandivali West, Mumbai 400067, registered with MahaRERA as PR1180002500146. It was launched in June 2025. It has 96 units in 1 building: 87 homes (1, 2, 3 and 4 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 96 units, 70 are for sale and 26 are rehab units for existing members.

Its registered possession date is May 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 14% complete, final finishes not started.

31 units booked out of 70 units for sale (44%). Since the July 2026 update, 15 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 14%.