The Adhiraj, Santacruz West

by Sagar Manoj Goradia · Santacruz West, Mumbai 400054 · Map

Launched
Apr 20252 yrs 8 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
5 of 956% · 15 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 9 units

Rehab15 units for existing members

Total 24 units. Rehab units are not for sale.

Project facts

1 RK
1
2 BHK
11
3 BHK
10
Other units
2
Total units
24
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%5
100%75%0%4
0%0%0%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400054

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths2 yrs 10 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2027Mar 2028
Concrete structure (RCC)100%12%
Units booked (free sale)56%0%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

The Adhiraj by Sagar Manoj Goradia is a 24-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in April 2025 with possession due in December 2027. 5 units booked out of 9 units for sale. The concrete structure (RCC) is complete.

Read full summary

The Adhiraj is a BMC-sanctioned project by Sagar Manoj Goradia in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800079982. It was launched in April 2025. It has 24 units in 1 building: 22 homes (1 RK, 2 BHK and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 24 units, 9 are for sale and 15 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

5 units booked out of 9 units for sale (56%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 75% to 100%.