Siddhi Elite, Vile Parle East
by Mehul Ratilal Shah · Vile Parle East, Mumbai 400057 · Map
- Launched
- Apr 20251 yr 8 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 50%Mid-construction
- Booked (free sale)
- 0 of 120% · 8 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 12 units
Rehab8 units for existing members
Total 20 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 8
- 2 BHK
- 9
- Other units
- 2
- Total units
- 20
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 12
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 0 | |
| 100% | 50% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 8 mths | 2 yrs 9 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Mar 2028 |
| Concrete structure (RCC) | 50% | 40% |
| Units booked (free sale) | 0% | 7% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Pruthvi Ashakiran, Vile Parle East
- Sadasukh, Vile Parle East
- Suyash Eminence, Vile Parle East
- Sky Avenue, Vile Parle East
- Friends Trimbakeshwar Chs Ltd, Vile Parle East
- Dipti Jyot, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Pruthvi Ashakiran | April 2025 | August 2028 | 90% | 8 units booked out of 10 units for sale |
| Sadasukh | March 2025 | March 2027 | 70% | 1 unit booked out of 15 units for sale |
| Suyash Eminence | June 2025 | December 2027 | 11% | 0 units booked out of 1 unit for sale |
| Sky Avenue | June 2025 | December 2028 | 0% | – |
| Friends Trimbakeshwar Chs Ltd | June 2025 | March 2028 | 70% | 1 unit booked out of 9 units for sale |
| Dipti Jyot | June 2025 | March 2028 | 0% | 0 units booked out of 2 units for sale |
About this project
Siddhi Elite by Mehul Ratilal Shah is a 20-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in April 2025 with possession due in December 2026. 0 units booked out of 12 units for sale. The concrete structure (RCC) is 50% complete.
Read full summary
Siddhi Elite is a BMC-sanctioned project by Mehul Ratilal Shah in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800080025. It was launched in April 2025. It has 20 units in 1 building: 18 homes (1 RK, 1 BHK and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 20 units, 12 are for sale and 8 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.
0 units booked out of 12 units for sale (0%).