by Dvasuyash Construction LLP · Vile Parle East, Mumbai 400057 · Map

Launched
Jun 20252 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
11%Mid-construction
Booked (free sale)
0 of 10% · 20 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 1 unit

Rehab20 units for existing members

Total 21 units. Rehab units are not for sale.

Project facts

1 RK
4
1 BHK
9
2 BHK
2
3 BHK
2
Other units
4
Total units
21
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
1
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)11%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 75%Jul 2026: Excavation 75%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 11%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 11%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%11%0%0
75%0%0%0
75%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 6 mths2 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027May 2028
Concrete structure (RCC)11%50%
Units booked (free sale)0%11%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Suyash Eminence by Dvasuyash Construction LLP is a 21-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in June 2025 with possession due in December 2027. 0 units booked out of 1 unit for sale. The concrete structure (RCC) is 11% complete.

Read full summary

Suyash Eminence is a BMC-sanctioned project by Dvasuyash Construction LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800080441. It was launched in June 2025. It has 21 units in 1 building: 17 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 1 is for sale and 20 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 11% complete, final finishes not started.

0 units booked out of 1 unit for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 11%.