Pruthvi Aura, Vile Parle East

by Pruthvi Enterprise · Vile Parle East, Mumbai 400057 · Map

Launched
Aug 20252 yrs 10 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
50%Mid-construction
Booked (free sale)
6 of 786% · 9 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale6 booked out of 7 units

Rehab9 units for existing members

Total 16 units. Rehab units are not for sale.

Project facts

1 BHK
3
2 BHK
2
3 BHK
10
5+ BHK
1
Total units
16
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
7
Rehab units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 50%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%6
100%10%0%5
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths2 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2028Jul 2028
Concrete structure (RCC)50%6%
Units booked (free sale)86%6%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pruthvi Aura by Pruthvi Enterprise is a 16-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in August 2025 with possession due in June 2028. 6 units booked out of 7 units for sale. The concrete structure (RCC) is 50% complete.

Read full summary

Pruthvi Aura is a BMC-sanctioned project by Pruthvi Enterprise in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800080934. It was launched in August 2025. It has 16 units in 1 building, with 1, 2, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 16 units, 7 are for sale and 9 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.

6 units booked out of 7 units for sale (86%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 10% to 50%.