Regent Priyadarshani, Vile Parle East

by Regent Spaces · Vile Parle East, Mumbai 400057 · Map

Launched
Sep 20253 yrs 6 mths promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
67%Mid-construction
Booked (free sale)
2 of 922% · 13 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 9 units

Rehab13 units for existing members

Total 22 units. Rehab units are not for sale.

Project facts

2 BHK
8
3 BHK
14
Total units
22
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)67%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 67%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 67%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%0%2
100%0%0%2
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths2 yrs 1 mth
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2029Jan 2028
Concrete structure (RCC)67%25%
Units booked (free sale)22%35%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Regent Priyadarshani by Regent Spaces is a 22-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in September 2025 with possession due in March 2029. 2 units booked out of 9 units for sale. The concrete structure (RCC) is 67% complete.

Read full summary

Regent Priyadarshani is a BMC-sanctioned project by Regent Spaces in Vile Parle East, Mumbai 400057, registered with MahaRERA as PR1180002500739. It was launched in September 2025. It has 22 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 22 units, 9 are for sale and 13 are rehab units for existing members.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 67% complete, final finishes not started.

2 units booked out of 9 units for sale (22%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 67%.