Shreepati Aradhana, Kalbadevi
Ready to moveLapsed
by Shreepati Build Infra Investment Limited · Kalbadevi, Mumbai 400002 · Map
- Launched
- Jul 20172 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2022Extended by 3 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 30.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Total units
- –
- Buildings
- 3
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | – | |
| 100% | 100% | 99% | – | |
| 100% | 100% | 92% | 37 |
"–" means MahaRERA shows no figure for that update.
About this project
Shreepati Aradhana by Shreepati Build Infra Investment Limited is a project in Kalbadevi, Mumbai 400002, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Shreepati Aradhana is a project by Shreepati Build Infra Investment Limited in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900000558. It was launched in July 2017. Its MahaRERA status is Lapsed.
Possession was due in December 2022, after an extension of 3 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
Shreepati's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 2,745 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 5 |
| Possession date extended on the builder's application | 3 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Shreepati projects | 8 (3 of 9 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.