Shreepati Aradhana, Kalbadevi

Ready to moveLapsed

by Shreepati Build Infra Investment Limited · Kalbadevi, Mumbai 400002 · Map

Launched
Jul 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Dec 2022Extended by 3 yrsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
30.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
3
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services99%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 92%Dec 2025: Final finishes 99%Jul 2026: Final finishes 99%Excavation 100%Concrete structure (RCC) 100%Final finishes 99%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%–
100%100%99%–
100%100%92%37

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shreepati Aradhana by Shreepati Build Infra Investment Limited is a project in Kalbadevi, Mumbai 400002, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Shreepati Aradhana is a project by Shreepati Build Infra Investment Limited in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900000558. It was launched in July 2017. Its MahaRERA status is Lapsed.

Possession was due in December 2022, after an extension of 3 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

Shreepati's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA9
Total units across these projects2,745
Completed without extending the possession date1
Completed after an extension0
Lapsed3
Under construction5
Possession date extended on the builder's application3
Typical time from launch to 100% structure7 years 5 months
MahaRERA complaints (filed by or against the builder), all Shreepati projects8 (3 of 9 projects)

See all Shreepati projects →