Shreepati Coronet, Mazgaon
by Shreepati Build Infra Investment Limited · Mazgaon, Mumbai 400010 · Map
- Launched
- Jul 20172 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 7 yrs
- Concrete structure
- 50%Mid-construction
- Booked
- 13 of 2945%
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 3 BHK
- 28
- Total units
- 29
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 75% | 13 | |
| 100% | 50% | 75% | – | |
| 100% | 50% | 75% | – | |
| 100% | 50% | 75% | 13 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400010
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 3 yrs 8 mths |
| Possession date extended | By 7 yrs | 2 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Aug 2021 |
| Concrete structure (RCC) | 50% | 86% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Halima Residency, Mazgaon
- Belvedre Hills, Mazgaon
- Bismillah Sra Chs Ltd, Mazgaon
- Nakhwa Heritage, Mazgaon
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Halima Residency | August 2017 | December 2027 | 73% | 0 units booked out of total 35 units |
| Belvedre Hills | August 2017 | April 2020 | 100% | – |
| Bismillah Sra Chs Ltd | September 2017 | December 2022 | 100% | 17 units booked out of total 17 units |
| Nakhwa Heritage | November 2017 | December 2019 | 25% | – |
About this project
Shreepati Coronet by Shreepati Build Infra Investment Limited is a 29-unit project in Mazgaon, Mumbai 400010, launched in July 2017 with possession due in December 2026. 13 units booked out of total 29 units. The concrete structure (RCC) is 50% complete.
Read full summary
Shreepati Coronet is a project by Shreepati Build Infra Investment Limited in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900000623. It was launched in July 2017. It has 29 units in 2 buildings, with 1 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 7 years from the original December 2019. Construction: excavation complete, structure (RCC) 50% complete, final finishes 75% complete.
13 units booked out of total 29 units (45%).
Shreepati's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 2,745 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 5 |
| Possession date extended on the builder's application | 3 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Shreepati projects | 8 (3 of 9 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.