Ksa Royale, Mumbai Central

by M/S.Ksa Developers · Mumbai Central, Mumbai 400008 · Map

Launched
Jul 2017First of 2 phases
Possession (MahaRERA)
Mar 2024 – Dec 2029Extended in 1 of 2 phases
Concrete structure
40%Weighted across 2 phases
Booked (free sale)
–
Buildings
20.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale122 units; booked –

Rehab50 units for existing members

Total 172 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
153
2 BHK
17
3 BHK
1
Total units
172
Buildings
2
Land
0.2 acres
Phases
2
MahaRERA complaints
0
Free-sale units
122
Rehab units
50

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Ksa Royale
Ready to move Lapsed
P5190000120668100%–
KSA Royale B Wing
Early stage
P519000794541040%6%
Show updates by phase

Ksa Royale (P51900001206)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%68

"–" means MahaRERA shows no figure for that update.

KSA Royale B Wing (P51900079454)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%6
0%0%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation40%
Concrete structure (slabs)40%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 40%Jul 2026: Excavation 40%Oct 2026: Excavation 40%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 40%Oct 2026: Concrete structure (RCC) 40%Dec 2025: Final finishes 40%Jul 2026: Final finishes 40%Oct 2026: Final finishes 40%Excavation 40%Concrete structure (RCC) 40%Final finishes 40%

How to read construction stages

Compared with 5 similar projects in PIN 400008

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400008
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths5 yrs 4 mths
Possession date extendedYes4 of 5
Possession date (MahaRERA)Mar 2024 – Dec 2029Apr 2027
Concrete structure (RCC)40%100%
Units booked (free sale)–51%
MahaRERA complaints (filed by or against the builder)02

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Ksa Royale by M/S.Ksa Developers is a 172-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, registered with MahaRERA in 2 phases, with possession dates from March 2024 to December 2029. The concrete structure (RCC) is 40% complete.

Read full summary

Ksa Royale is a BMC-sanctioned project by M/S.Ksa Developers in Mumbai Central, Mumbai 400008, registered with MahaRERA as 2 phases (P51900001206, P51900079454). The first phase was launched in July 2017. Together the phases have 172 units in 2 buildings, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active. Of the 172 units, 122 are for sale and 50 are rehab units for existing members.

The phases' registered possession dates run from March 2024 to December 2029; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 40% complete and final finishes 40% complete. Neither phase has its structure complete.