Golden Residency, Mumbai Central

by Golden Realty · Mumbai Central, Mumbai 400008 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 4 yrs 4 mths
Concrete structure
100%Nearing possession
Booked
119 of 30739%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
95
1 BHK
197
Other units
15
Total units
307
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%119
100%100%0%–
100%100%0%–
100%100%0%119

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400008

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400008
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths5 yrs 4 mths
Possession date extendedBy 4 yrs 4 mths3 of 4
Possession date (MahaRERA)Apr 2027Nov 2024
Concrete structure (RCC)100%100%
MahaRERA complaints (filed by or against the builder)02

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Golden Residency by Golden Realty is a 307-unit project in Mumbai Central, Mumbai 400008, launched in August 2017 with possession due in April 2027. 119 units booked out of total 307 units. The concrete structure (RCC) is complete.

Read full summary

Golden Residency is a project by Golden Realty in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900007576. It was launched in August 2017. It has 307 units in 1 building: 292 homes (1 RK and 1 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 4 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes not started.

119 units booked out of total 307 units (39%).