Fuego, Mumbai Central

Ready to move

by Hilton Infrastructure · Mumbai Central, Mumbai 400008 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Oct 2027Extended by 4 yrs 10 mths
Concrete structure
100%Ready to move
Booked
125 of 22057% · 124 in Jul 2026
Buildings
31 acre
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
66
2 BHK
153
Other units
1
Total units
220
Buildings
3
Land
1 acre
Phases
1
MahaRERA complaints
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services93%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 93%Jul 2026: Final finishes 93%Oct 2026: Final finishes 93%Excavation 100%Concrete structure (RCC) 100%Final finishes 93%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%93%125
100%100%93%124
100%100%93%122
100%100%90%121

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400008

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400008
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths5 yrs 4 mths
Possession date extendedBy 4 yrs 10 mths4 of 5
Possession date (MahaRERA)Oct 2027Jun 2025
Concrete structure (RCC)100%100%
Units booked57%39%
MahaRERA complaints (filed by or against the builder)81

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Fuego by Hilton Infrastructure is a 220-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in August 2017 with possession due in October 2027. 125 units booked out of total 220 units. The concrete structure (RCC) is complete.

Read full summary

Fuego is a BMC-sanctioned project by Hilton Infrastructure in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900009939. It was launched in August 2017. It has 220 units in 3 buildings: 219 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2027, extended by 4 years 10 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 93% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

125 units booked out of total 220 units (57%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from December 2023 to October 2027.