Tridhaatu Arista - Redevelopment of Shanti Niwas, Matunga
by Tridhaatu Builders LLP · Matunga, Mumbai 400019 · Map
- Launched
- Jul 20173 yrs 11 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 5 yrs 9 mths
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 11 of 11100% · 10 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale11 booked out of 11 units
Rehab10 units for existing members
Total 21 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 2
- 3 BHK
- 16
- 4 BHK
- 1
- 5+ BHK
- 1
- Total units
- 21
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 11
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 11 | |
| 100% | 90% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400019
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 11 mths | 2 yrs 4 mths |
| Possession date extended | By 5 yrs 9 mths | 3 of 3 |
| Possession date (MahaRERA) | Mar 2027 | Jun 2025 |
| Concrete structure (RCC) | 90% | 100% |
| MahaRERA complaints (filed by or against the builder) | 1 | 1 |
The 3 projects
- Heritage Heights, Matunga
- Gulraj Paradise, Matunga
- Sangeet Jyoti, Matunga
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Heritage Heights | August 2017 | December 2020 | 100% | – |
| Gulraj Paradise | August 2017 | September 2026 | 92% | 32 units booked out of total 35 units |
| Sangeet Jyoti | August 2017 | June 2025 | 100% | 5 units booked out of total 11 units |
About this project
Tridhaatu Arista - Redevelopment of Shanti Niwas by Tridhaatu Builders LLP is a 21-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in July 2017 with possession due in March 2027. 11 units booked out of 11 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Tridhaatu Arista - Redevelopment of Shanti Niwas is a BMC-sanctioned project by Tridhaatu Builders LLP in Matunga, Mumbai 400019, registered with MahaRERA as P51900001764. It was launched in July 2017. It has 21 units in 1 building, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 11 are for sale and 10 are rehab units for existing members.
Its registered possession date is March 2027, extended by 5 years 9 months from the original June 2021. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
11 units booked out of 11 units for sale (100%). Since the December 2024 update, 11 more units have been booked and the possession date has moved from June 2021 to March 2027.
Tridhaatu's track record in Mumbai
MahaRERA projects registered 2017–2023 in Mumbai
| Projects registered with MahaRERA | 12 |
|---|---|
| Total units across these projects | 649 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 1 |
| Lapsed | 6 |
| Under construction | 4 |
| Possession date extended on the builder's application | 6 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Tridhaatu projects | 33 (10 of 12 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.