Gulraj Paradise, Matunga

Lapsed

by M/S Reliable Construction · Matunga, Mumbai 400019 · Map

Launched
Aug 20173 yrs 10 mths originally promised
Possession (MahaRERA)
Sep 2026Extended by 5 yrs 3 mthsWhat does Lapsed mean?
Concrete structure
92%Mid-construction
Booked
32 of 3591%
Buildings
21.4 acres
MahaRERA complaints
18Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
27
Other units
8
Total units
35
Buildings
2
Land
1.4 acres
Phases
1
MahaRERA complaints
18
Reserved units
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 81%Dec 2025: Concrete structure (RCC) 92%Jul 2026: Concrete structure (RCC) 92%Oct 2026: Concrete structure (RCC) 92%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 92%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%0%32
100%92%0%32
100%92%0%32
100%81%0%329

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400019

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400019
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths2 yrs 4 mths
Possession date extendedBy 5 yrs 3 mths3 of 3
Possession date (MahaRERA)Sep 2026Jun 2025
Concrete structure (RCC)92%100%
MahaRERA complaints (filed by or against the builder)181

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Gulraj Paradise by M/S Reliable Construction is a 35-unit SRA-sanctioned project in Matunga, Mumbai 400019, launched in August 2017; its MahaRERA registration has lapsed. 32 units booked out of total 35 units. The concrete structure (RCC) is 92% complete.

Read full summary

Gulraj Paradise is an SRA-sanctioned project by M/S Reliable Construction in Matunga, Mumbai 400019, registered with MahaRERA as P51800004371. It was launched in August 2017. It has 35 units in 2 buildings: 27 homes (1 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2026, after an extension of 5 years 3 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 92% complete, final finishes not started.

32 units booked out of total 35 units (91%).